Australia court halts Santos' $3.6 billion Barossa gas pipeline works

Published 11/02/2023, 12:25 AM
Updated 11/02/2023, 11:42 AM
© Reuters. FILE PHOTO: The logo of Australian oil and gas exploration and production company Santos is displayed during the LNG 2023 energy trade show in Vancouver, British Columbia, Canada, July 12, 2023. REUTERS/Chris Helgren/File Photo
STO
-

By Renju Jose and Ayushman Ojha

SYDNEY (Reuters) -Santos said on Thursday an Australian court has granted an interim injunction preventing it from starting work on laying undersea pipelines on its $3.6 billion Barossa gas project off northern Australia.

The ruling comes after Simon Munkara, a traditional land owner from the Tiwi Islands, lodged proceedings with the Federal Court of Australia to halt the pipeline works until its impact and risk to underwater cultural heritage were properly assessed.

Law firm Environmental Defenders Office (EDO) represented Munkara and other indigenous elders from the Tiwi Islands who had urged the government to make an urgent declaration to block the pipeline construction.

The pipeline would cause significant damage to ancient burial grounds, aboriginal art and other sacred ancestral sites, Munkara said, according to a statement from EDO.

The court will sit on Nov. 13 to determine whether to extend the injunction until the final hearing, which will be held on an expedited basis.

Santos, which aims to start producing gas from Barossa in the first half of 2025, said its guidance on cost and schedule for the project remained unchanged. It will continue to defend the court proceedings.

Australia's offshore regulator ordered Santos in January to evaluate the environmental risks to underwater indigenous cultural heritage before starting pipeline work though it did not prohibit the start of work.

Santos has said, citing an independent expert, that there were no specific underwater cultural heritage sites along the planned route of the pipeline.

A Santos ship was hours away from beginning work on the pipeline, lawyers for Munkara told the court. Santos said the vessel will remain at its current location but no pipeline works will be conducted during the interim injunction.

© Reuters. FILE PHOTO: The logo of Australian oil and gas exploration and production company Santos is displayed during the LNG 2023 energy trade show in Vancouver, British Columbia, Canada, July 12, 2023. REUTERS/Chris Helgren/File Photo

The court's ruling poses another hurdle for the project and a win for Indigenous groups opposing fossil fuel developments, who have been raising concerns it could damage the environment and their cultural heritage.

In September, the federal court halted approval for Woodside (OTC:WOPEY) to conduct seismic blasting under the seabed for its $12 billion Scarborough gas project after a legal challenge by an Indigenous woman.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.