US court questions another Equitrans Mountain Valley natgas pipe permit

Published 05/26/2023, 03:48 PM
Updated 05/26/2023, 03:50 PM
© Reuters. FILE PHOTO: Lengths of pipe wait to be laid in the ground along the under-construction Mountain Valley Pipeline near Elliston, Virginia, U.S. September 29, 2019. Picture taken September 29, 2019. REUTERS/Charles Mostoller
ED
-
NG
-
NEE
-
ALA
-
ETRN
-

(Reuters) - U.S. energy company Equitrans Midstream (NYSE:ETRN) Corp's long-delayed $6.6 billion Mountain Valley natural gas pipeline from West Virginia to Virginia received another negative court ruling on Friday.

The U.S. Court of Appeals for the District of Columbia Circuit ruled the U.S. Federal Energy Regulatory Commission (FERC) "inadequately explained its decision not to prepare a supplemental environmental impact statement."

The statement would address "unexpectedly severe erosion and sedimentation along the pipeline’s right-of-way."

The Court remanded the case back to FERC to either "prepare a supplemental environmental impact statement or to better explain why one is unnecessary."

The case was brought by the Sierra Club and other environmental groups opposed to the project.

"We see this ruling as creating an additional hurdle to restarting construction when (Mountain Valley) reacquires its outstanding permits this year, as it could force a longer review ... and could push the project’s completion into 2024," said analyst at ClearView Energy Partners, a research firm.

Equitrans said it was reviewing the decision, without providing any additional details. Its stock rose about 4% to a 12-week high of $6.14 per share in late Friday trading.

In early May, it said it could finish the pipe by the end of 2023, but noted "there remains significant risk and uncertainty, including regarding current and likely litigation."

The U.S. Fourth Circuit Court of Appeals, which has vacated several of the project's federal and state permits - some more than once - is still hearing lawsuits, including a challenge against authorizations from the U.S. Fish and Wildlife Service.

Equitrans is waiting for new authorizations from the West Virginia Department of Environmental Protection, the U.S. Army Corps of Engineers and FERC.

In addition to pursuing permitting the regular way, Equitrans said it "continues to support the potential enactment of federal energy infrastructure permitting reform legislation that specifically requires completion of the (Mountain Valley) project."

© Reuters. FILE PHOTO: Lengths of pipe wait to be laid in the ground along the under-construction Mountain Valley Pipeline near Elliston, Virginia, U.S. September 29, 2019. Picture taken September 29, 2019. REUTERS/Charles Mostoller

When Mountain Valley construction started in February 2018, Equitrans estimated the 303-mile (488-km), 2-billion-cubic-feet-per-day (bcfd) project would cost about $3.5 billion and enter service by late 2018.

Mountain Valley is owned by units of Equitrans, NextEra Energy Inc (NYSE:NEE), Consolidated Edison Inc (NYSE:ED), AltaGas (TSX:ALA) Ltd and RGC Resources Inc.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.