By Tom Hals

(Reuters) - Toshiba Corp has agreed to pay $2.168 billion to walk away from two unfinished nuclear reactors in South Carolina being built by its Westinghouse subsidiary, according to a statement by the owners of project.

SCANA Corp (N:SCG) and its partner, state-owned utility Santee Cooper, said Toshiba will make the payments in installments beginning in October and ending in September 2022.

Toshiba's Westinghouse Electric Co filed for bankruptcy in March, overwhelmed by the cost overruns at the VC Summer plant in South Carolina and a similar unfinished nuclear project known as Vogtle in Georgia. The projects are years behind schedule.

The agreement allows Toshiba and its Westinghouse unit to exit the nuclear construction business and caps Toshiba's liability for guaranteeing that Westinghouse complete the VC Summer contract.

Toshiba reached a similar agreement for $3.7 billion in June with the utilities, led by a unit of Southern Co (N:SO), that own the Vogtle project.

Toshiba has warned that losses from Westinghouse threaten its future and it is considering bids for its flash memory chip unit, worth around $18 billion, to raise capital.

The owners of the VC Summer project said on Thursday they expect the cost of completing the project will "materially exceed" Westinghouse's estimates and the payments due from Toshiba. They said they hope to decide soon whether they will continue with the two projects, modify them or abandon them.

Westinghouse is expected to deliver this week a five-year business plan to its lender, an affiliate of Apollo Global Management (N:APO). That plan will help shape bids for Westinghouse, which has attracted the interest of U.S. private equity firms.

As part of that plan, Westinghouse is expected to reach an agreement with SCANA under which it will continue to provide engineering and other services. Westinghouse has a similar agreement in place with the owners of the Vogtle plant.

Westinghouse asked the U.S. Bankruptcy Court in Manhattan, New York, on Wednesday to give it until Dec. 6 to file a plan of reorganization. The company said it needed more time in part due to talks with SCANA.

The request will be heard by the court on Sept. 7.

The Georgia and South Carolina plants were the first new nuclear power projects in the United States in three decades.

© Reuters. FILE PHOTO: Logo of Toshiba Corp is seen as Window cleaners work on the company's headquarters in Tokyo

However, the projects have been dogged by design problems, disagreements with regulators and poor quality work by Westinghouse's partners.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.