INTERVIEW-Kenya wind power plan gets govt's support letters

Published 01/20/2011, 06:30 AM
Updated 01/20/2011, 06:32 AM

* Lenders comfortable with the letters of support

* Govt can't give guarantees

* Financial close likely within 6-8 months

By Helen Nyambura-Mwaura

NAIROBI, Jan 20 (Reuters) - Plans for a delayed 300 MW wind farm in Kenya can now proceed after lenders agreed to rely on the government's assurance that it backed the plan, instead of proper guarantees, the chairman of the project said.

Kenya's government has been scratching its head over how to deal with demand from lenders for financial guarantees. Kenyan law do not allow the Treasury to put down a security for a private venture.

Once complete, the Lake Turkana Wind Power (LTWP) project will sell its output to the country's sole power distributor Kenya Power that is majority owned by the government.

The two have already agreed on feed-in tariffs of 7.22 euro cents per kilowatt hour for 20 years.

"Guarantees, we are not being given. What we are getting is a letter of comfort, or support, from the ministry of finance. This has now been agreed with the lenders as an acceptable format so we can move forward," Carlo van Wageningen, chairman of LTWP, told Reuters in an interview.

Other independent power producers awaiting government guarantees will get similar letters, he said.

"It is a format acceptable with the lenders. They are comfortable."

Lenders are lined up to provide 430 million euros ($580 million) for the Turkana project, while equity will cough up another 185 million euros.

African Development Bank (AfDB) is the lead arranger and is working with two co-arrangers, South Africa's Nedbank and Standard Bank - London, he said.

Financial closure on the deal will take another six to eight months, van Wageningen told Reuters late on Wednesday, while the first 50 MW are expected to come onstream 19 months after groundbreaking, likely in September.

LTWP's largest engineering, procurement and construction contract will be for the 358 turbines -- to be procured from Danish Vestas Wind Systems -- it needs for the farm and a service agreement for 15 years.

Other contracts to be signed include upgrading a 157 km (98 miles) stretch of road connecting the project site in Kenya's remote northwestern corner to the nearest tarmac road.

Other construction contracts to be arranged are for substations, networking the individual turbines to one another, a village for about 150 staff members and a 428 km transmission line to conduct the electricity to the national grid.

"We are very happy now that we can move. The ball is now back in our court," van Wageningen said. (Editing by Richard Lough and James Jukwey)

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.