London's Crossrail puts back opening to March 2021 at the latest

Published 04/25/2019, 04:05 PM
© Reuters. FILE PHOTO: Britain's Queen Elizabeth attends the formal unveiling of the new logo for Crossrail, which is to be named the Elizabeth line, at the construction site of the Bond Street station in central London

LONDON (Reuters) - London's new flagship rail line connecting Heathrow Airport to the Canary Wharf financial district may not now open before 2021, more than two years behind schedule, the Crossrail project said on Thursday.

Billed as Europe's most ambitious infrastructure project, the line, which runs under the capital, was supposed to open in December 2018, but was delayed shortly before the launch by problems with testing and the completion of signaling work.

When open, the Elizabeth Line, as the link has been named, will connect destinations such as Heathrow west of the city with the rail hub of Paddington, shopping districts such as Bond Street, Canary Wharf in the east, and beyond.

It is expected to carry about 500,000 passengers a day and alleviate pressure on the Victorian-era metro (subway) network, the Underground or Tube. An initial budget of around 15 billion pounds ($19 billion) has risen to 17.6 billion pounds.

"Crossrail is an immensely complex project and there will be challenges ahead," new chief executive Mark Wild said. "This new plan will ... allow this fantastic new railway to open around the end of next year."

Among the remaining tasks are building and testing the software to integrate the train operating systems with signaling systems; testing station and tunnel systems; and running train trials.

Crossrail said it had identified a six-month window, with a midpoint at the end of 2020, for it to open the central section of the line between Paddington and Abbey Wood to the east of London. All stations on the route will open apart from Bond Street, which has further problems.

Once the section has opened, trains will run on the whole line as soon as possible. Crossrail will also provide more specific estimates as the line gets nearer to completion.

Crossrail's chairman said he knew it needed to rebuild trust with its stakeholders after the lengthy delays.

© Reuters. FILE PHOTO: Britain's Queen Elizabeth attends the formal unveiling of the new logo for Crossrail, which is to be named the Elizabeth line, at the construction site of the Bond Street station in central London

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.