Trump tries fresh approach with long-delayed Keystone XL pipeline

Published 03/29/2019, 05:57 PM
Updated 03/29/2019, 06:00 PM
© Reuters. FILE PHOTO: An aerial view of an oilspill which shut down the Keystone pipeline between Canada and the United States in an agricultural area near Amherst South Dakota

By Timothy Gardner and Eric Beech

WASHINGTON (Reuters) - U.S. President Donald Trump on Friday signed a new permission for TransCanada Corp to build the long-delayed Keystone pipeline for imports of Canadian oil, replacing his previous permits in a fresh attempt to get around the blocking of the $8 billion project by a court in Montana.

In granting the permission in an executive order, Trump revoked a previous permit for the pipeline issued in March 2017 and an executive order approving the project he issued two days after taking office in January that year.

It was not immediately clear whether under the new approval the pipeline, which would carry 800,000 barrels per day of crude from Canada's oil sands to refineries along the U.S. Gulf of Mexico, would have to undergo extensive new environmental reviews.

The Keystone XL pipeline has been pending for more than a decade after environmental reviews and after former President Barack Obama rejected the project saying it would do little to benefit U.S. motorists and would contribute to global warming.

Friday's permission was the latest move in the Trump administration's pursuit of what it calls "energy dominance," or maximizing production of oil, gas and coal for domestic use and exports to allies and trading partners. The administration has rolled back environmental regulations on emissions from power plants and vehicles and opened up federal lands to drilling and mining.

Russ Girling, TransCanada's president and chief executive officer, said in a release that Trump "has been clear that he wants to create jobs and advance U.S. energy security and the Keystone XL pipeline does both of those things."

The pipeline faced numerous legal hurdles after several environmental groups sued the U.S. government over the 2017 presidential permit, and Keystone has been held up in the courts, most recently in Montana.

Judge Brian Morris of the U.S. District Court for Montana blocked construction of the pipeline in November last year.

Morris wrote in his ruling that a U.S. State Department environmental analysis “fell short of a ‘hard look’” at the cumulative effects of greenhouse gas emissions and the impact on Native American land resources.

The head of the Sierra Club green group said Trump was trying to bypass "bedrock" environmental laws for the benefit of a foreign pipeline company. "We will continue to pursue every available avenue to ensure that this pipeline is never built," said Michael Brune, the club's executive director.

© Reuters. FILE PHOTO: An aerial view of an oilspill which shut down the Keystone pipeline between Canada and the United States in an agricultural area near Amherst South Dakota

Analysts at ClearView Energy Partners said in a note that Trump's new permit might end delays related to further environmental review called for by the court, but that the project still faces hurdles in states it goes through including multiple water quality permits in South Dakota.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.