Canada regulator to make preliminary decision on Trans Mountain expansion tolls

Published 10/12/2023, 06:38 PM
Updated 10/12/2023, 06:40 PM
© Reuters. FILE PHOTO: A pipe yard servicing government-owned oil pipeline operator Trans Mountain is seen in Kamloops, British Columbia, Canada June 7, 2021. REUTERS/Jennifer Gauthier/File Photo
CNQ
-
CVE
-
TRP
-

By Ismail Shakil and Nia Williams

OTTAWA (Reuters) - The Canada Energy Regulator (CER) said on Thursday it will make a preliminary decision on Trans Mountain Corp's proposed shipping tolls for its oil pipeline expansion project this autumn, before holding a hearing on the tolls next year.

The timing of the decision aims to ensure interim tolls are in place when the pipeline expansion becomes operational, the regulator said in a statement.

The 590,000 barrel-per-day Trans Mountain expansion project (TMEP) will nearly triple the flow of oil from the province of Alberta to Canada's Pacific Coast and is expected to start operating late in the first quarter of 2024.

But shippers including Canadian Natural (NYSE:CNQ) Resources and Cenovus Energy (NYSE:CVE) are disputing the interim tolls proposed by Trans Mountain, arguing a portion of the base toll is too high.

Long-term shipping contracts cover 80% of the expansion project's capacity. The final tolls will impact the value of the pipeline when the Canadian government, which bought it in 2018 to ensure the expansion got built, puts it up for sale.

© Reuters. FILE PHOTO: A pipe yard servicing government-owned oil pipeline operator Trans Mountain is seen in Kamloops, British Columbia, Canada June 7, 2021. REUTERS/Jennifer Gauthier/File Photo

The CER said the hearing next year would look at issues including the "fairness and reasonableness" of existing tolling agreements with shippers and potential repercussions on Trans Mountain's financial standing.

"After service begins on the TMEP and final costs are known, Trans Mountain can request approval from the Commission of the CER for final tolls," the regulator said.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.