Canada paid high price for oil pipeline, faces delay risks: watchdog

Published 01/31/2019, 03:23 PM
© Reuters. Steel pipe to be used in the pipeline construction of Kinder Morgan Canada's Trans Mountain Expansion Project sit on rail cars at a stockpile site in Kamloops
KMI
-

By Rod Nickel

WINNIPEG, Manitoba (Reuters) - The Canadian government paid a high price for the Trans Mountain oil pipeline last summer, and delays in expanding it could reduce its resale value, a watchdog on the country's public finances said on Thursday.

Prime Minister Justin Trudeau's government purchased the Trans Mountain pipeline and a related expansion in August from Kinder Morgan (NYSE:KMI) Canada, fearing the company might abandon the capacity expansion. The project and others like it have faced stiff opposition in Canada from environmental groups and some local governments.

The Canadian government paid C$4.4 billion for the pipeline, related assets and the expansion project and intends to eventually sell it. The pipeline, running from Alberta's oil-gathering hub to the Vancouver, British Columbia area, is actually worth between C$3.6 billion and C$4.6 billion, the Parliamentary Budget Officer (PBO) said in an analysis.

Expansion is likely to cost C$9.3 billion for an in-service date at the end of 2021, the PBO wrote. Delays in construction, however, could reduce its value, it said.

Pierre-Olivier Herbert, a spokesperson for Finance Minister Bill Morneau, noted that the PBO's analysis did not include the benefit that moving oil to new markets would have on Canada's economy.

Most Canadian oil ships to the United States, but an expanded Trans Mountain may allow for greater Asian sales.

"When the political risks made it too difficult for the private sector to move forward, and after extensive due diligence, our government acquired the project," Herbert said.

Congested pipelines depressed Canadian oil prices severely last year, causing the Alberta government to impose mandatory production cuts this month.

The opposition Conservative Party chastised Trudeau in a statement saying he overpaid for the pipeline. In the past, the Conservatives have criticized the Liberal prime minister for doing too little to help the struggling industry.

© Reuters. Steel pipe to be used in the pipeline construction of Kinder Morgan Canada's Trans Mountain Expansion Project sit on rail cars at a stockpile site in Kamloops

An appeals court last summer overturned the government's approval for expanding Trans Mountain, saying the National Energy Board needed to address risks to marine life and government must better consult indigenous people. After a new review, the board is scheduled to report to Trudeau's cabinet next month.

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.