Canada's Trans Mountain ordered to stop pipeline work over environmental non-compliance

Published 11/02/2023, 03:33 PM
Updated 11/03/2023, 01:11 PM
© Reuters. A logo for TMX Group, which operates the Toronto Stock Exchange, is seen after the company announced it was shutting down all markets for the rest of the day after experiencing issues with trading on all its exchange platforms in Toronto, Ontario, Canada
TRP
-

By Nia Williams and Ismail Shakil

OTTAWA (Reuters) - The Canada Energy Regulator (CER) on Thursday ordered the Trans Mountain oil pipeline expansion project to stop work in a wetland area near Abbotsford, British Columbia, after inspectors found several environmental and safety-related non-compliances.

The order is the latest hold-up for the Canadian government-owned project, which has been plagued by years of regulatory delay, environmental opposition and massive cost overruns.

Some of the non-compliances include insufficient fencing to protect amphibians and unapproved vegetation clearing, the regulator said in a notice on its website.

The CER issued an Inspection Officer Order to Trans Mountain ordering it to stop work in the wetland until the non-compliances are corrected, investigate their root cause and conduct a safety inspection to confirm the site is safe for work.

Trans Mountain Corp, the Canadian government-owned corporation building the expansion project, said the order applies to a specific work area of about 800 metres.

"Trans Mountain is working hard to correct all non-compliances and to prevent reoccurrence," the company said in a statement, adding it "will seek to have the restrictions under the order lifted as soon as appropriate and according to the law."

Work on the oil pipeline expansion project is more than 95% complete, Trans Mountain said.

The 590,000 barrel-per-day expansion will nearly triple capacity on the existing pipeline running from Alberta to Canada's Pacific Coast. It is due to start operating early next year and will open up markets in Asia and on the U.S. West Coast for Canadian crude.

Prime Minister Justin Trudeau's Liberal government bought the pipeline in 2018 to ensure the expansion project went ahead. However, the cost has more than quadrupled since then to C$30.9 billion ($22.49 billion), partly due to delays in construction.

© Reuters. FILE PHOTO: A pipe yard servicing government-owned oil pipeline operator Trans Mountain is seen in Kamloops, British Columbia, Canada June 7, 2021.  REUTERS/Jennifer Gauthier/File Photo

In 2021, Trans Mountain was ordered to stop work for four months to protect hummingbird nests along a one-kilometer section of its route.

($1 = 1.3747 Canadian dollars) (This story has been refiled to change picture)

Latest comments

Risk Disclosure: Trading in financial instruments and/or cryptocurrencies involves high risks including the risk of losing some, or all, of your investment amount, and may not be suitable for all investors. Prices of cryptocurrencies are extremely volatile and may be affected by external factors such as financial, regulatory or political events. Trading on margin increases the financial risks.
Before deciding to trade in financial instrument or cryptocurrencies you should be fully informed of the risks and costs associated with trading the financial markets, carefully consider your investment objectives, level of experience, and risk appetite, and seek professional advice where needed.
Fusion Media would like to remind you that the data contained in this website is not necessarily real-time nor accurate. The data and prices on the website are not necessarily provided by any market or exchange, but may be provided by market makers, and so prices may not be accurate and may differ from the actual price at any given market, meaning prices are indicative and not appropriate for trading purposes. Fusion Media and any provider of the data contained in this website will not accept liability for any loss or damage as a result of your trading, or your reliance on the information contained within this website.
It is prohibited to use, store, reproduce, display, modify, transmit or distribute the data contained in this website without the explicit prior written permission of Fusion Media and/or the data provider. All intellectual property rights are reserved by the providers and/or the exchange providing the data contained in this website.
Fusion Media may be compensated by the advertisers that appear on the website, based on your interaction with the advertisements or advertisers.
© 2007-2024 - Fusion Media Limited. All Rights Reserved.